1300
Installed Capacity (kW)
3500
Yearly Production (MWh)
1000
UK households powered
Turbine Type: PeltonIn operation site 2012
The Holdalbekk hydroelectric power plant is located in the Vinje municipality in Telemark. The plant was completed in October 2012, with approximately 18 million NOK invested. Holdalbekk's catchment area is 9 km², providing an annual production of 3.5 GW, with an installed capacity of 1.3 MW.
The turbine operates a 214 meters high waterfall, with a maximum flow of 0,79 m3/s